Section I: LAER/BACT Determination for Application No. 324505

Basic Equipment or Process: Spray Booth

1. Basic Equipment

1a. Manufacturer: Dial-a-Temp

1b. Type: Dry Filter

1c. Model: Custom

1d. Style: Floor

1e. Types(s) of Parts Coated

Skylight domes (fiberglass)

1f. Types of Coating/Adhesive/Solvent Used

Polyester resin & gelcoat

1g. Applicable AQMD Regulation XI Rules

Rule 1162 - Polyester Resin Operations

Rule 1171 - Solvent Cleaning Operations

1h. Cost

Unknown

Source of Cost Data:

2. Basic Equipment Rating/Size – Particulate Equipment

2a. Size/Dimension/Capacity

1 - 10' W. x 2' D. x 8' H.

2 - 10' W. x 2' D. x 8' H.

3 - 10' W. x 2' D. x 8' H.

4 - 10'-4" W. x 10'-10" D. x 8'-5" H.

2b. Blowers

1 - 1@ 2 HP

2 - 1@ 2 HP

3 - 1@ 2 HP

4 - 1@ 2 HP

2c. Total Flow Rate: 17000

2d. Filters

1 - 36@ 20" x 20"

2 - 36@ 20" x 20"

3 - 30@ 20" x 20"

4 - 24@ 20" x 20"

2e. Normal Operating Condition

24 hrs/day, 7 days/wk, 52 wks/yr


3. Company Information

3a. Name: Bristol Fiberlite Industries

3b. Address: 401 E Goetz Ave

City: Santa Ana

State: CA

Zip: 92707

3c. Contact Person: Richard Coury, Operations Mgr.

3d. Phone No.: (714)540-8966 x275

4. Permit Information

4a. Agency

South Coast AQMD

4b. Agency Contact Person

Desh Jain

4c. Phone No: (909) 396-2555

4d. Permit to Construct Information

P/C No.: 324505

Issuance Date: 5-28-97

4e. Start-Up Date: 3/98

4f. Permit to Operate Information

P/O No. pending

Issuance Date:

5. Emission Information

5a. Permit Limit

5a1. Permit Limit

264 lb/day VOC after control

5a2. BACT/LAER Determination

The BACT/LAER determination for this application is a combination of a concentrator and a thermal oxidizer

5b. Control Technology

5b1. Manufacturer/Supplier

Ship & Shore

5b2. Description: Name of Control(s):

Three resin spray stations and one gel coat spray station are vented to the rotary carbon adsorber concentrator (11,400 pounds of carbon). The thermal oxidizer has a 1.6 MM Btu/hr natural gas fired burner. The carbon is regenerated by steam, supplied by a waste heat boiler.

5b3. Control Equipment Permit Application Data

P/C No .: 324505
P/C Issuance Date: 5/28/97
P/O No.: pending
P/O Issuance Date:

5b5. Warranty

Unknown

5b7. Secondary Pollutant

NOx 0.2 lb/hr, CO 0.05 lb/hr

5b9. Limitations

5b11. Operating History

Operating since 3/98

5b13. Source Test Conditions/Performance Data

Report is under review by AQMD (Source Testing Team).

5b4. Waste Air Flow to Control Equipment

Flow Rate: 17000

Actual VOC Loading:

Inlet Blower: 60 H.P.

5b6. Primary Pollutant

VOC

5b8. Space Requirement

Unknown

5b10. Location of Prior Demonstration & Agency Facility: Unknown Contact Person: Unknown Phone Number: Unknown Agency: Unknown

Address: Unknown Permit Number: Unknown Contact Person: Unknown

5b12. Source Test/Performance Data Analysis

Date of Source Test:
Capture Efficiency:
Destruction Efficiency:
Overall Efficiency:

Performance Data: Report is being review by Source Testing team.

5c. Cost

5c1. Control Equipment Cost

Capital: $463,750

Installation: Unknown

Capital + Installation: Unknown

Source of Cost Data:

5c2. Annual Operational/Maintenance Cost

Unknown

Source of Cost Data:

5d. Demonstration of Compliance

5d1. Date of Field Evaluation

5d3. Compliance Demonstration

5d5. No. of Violations

5d2. AQMD Staff Performing Field Evaluation

Engineer’s Name: Desh Jain

Inspector’s Name: Marian Coleman

5d4. Variance

No. of Variances:

Causes:

5d6. Frequency of Maintenance

6. Comment