PROPOSAL:
Amend Rule 1309.1 – Priority Reserve
SYNOPSIS:
Technical amendments are proposed to allow a critical public works
project access to the Priority Reserve for emission credits. This
technical amendment will allow a critical public works project that
primarily generates electricity to pump water to maintain the integrity of
a municipality or significant portion thereof access to the Priority
Reserve. This project was specifically listed in the staff report for the
November 2001 amendments allowing electrical generation facilities access
to the Priority Reserve subject to specific criteria and requirements.
COMMITTEE:
Stationary Source, April 26, 2002
RECOMMENDED ACTION:
Adopt the attached resolution:
- Certifying the Addendum to the November 2001 Final Environmental
Assessment (EA) for Proposed Amended Rule 1309.1
- Amending Rule 1309.1
Barry R. Wallerstein, D.Env.
Executive Officer
Background
Staff is proposing a technical amendment to Rule 1309.1 to include a
critical public works project for eligibility for Priority Reserve credits.
This project was identified in the staff report for the November 2001
amendments as a project that would receive credits from the Priority
Reserve.
This project is a critical public works project that primarily generates
electricity to pump water to prevent subsidence and maintain the integrity
of a municipality or significant portion thereof. While this project was
expected to receive credits from the Priority Reserve, the rule language as
adopted would disqualify this project. The purpose of this amendment is to
correct that problem and allow this project access to the Priority Reserve.
The project in question is the THUMS Long Beach electrical generating
project which will generate electricity for oil field activities and to pump
water to prevent subsidence that would otherwise result from those
activities. The eligibility criteria and requirements for electrical
generation facilities (EGFs), including paying a mitigation fee, will also
apply to this project.
Staff has prepared an addendum to the November 2001 Final EA for Rule
1309.1, demonstrating no additional impacts. There are no excess emissions
nor any environmental or socioeconomic impacts associated with this
amendment.
Proposal
The proposed amendment changes the definition of qualified electrical
generation projects to enable this actual public works project access to the
Priority Reserve. Thus, projects less than 50 MegaWatts (MW) that generate a
substantial portion of their electricity to pump water to maintain the
integrity of the surface elevation of a municipality or significant portion
thereof would be included as a qualified EGF.
The project will still be subject to all other aspects of NSR including
modeling, offsets for non-RECLAIM pollutants, RECLAIM, and BACT or LAER. All
other applicable SCAQMD rules and regulations such as toxics and prohibitory
rules would continue to apply to projects.
The following requirements apply to projects receiving credits from the
Priority Reserve:
| – |
Modifying all of the electrical generating facilities (EGF's)
sources to BARCT for the pollutant(s) obtained (if applicable) not later
than 3 years after issuance of the permit for the new source(s), and |
| – |
Paying a non-refundable mitigation fee of $8,900 per pound per day
for each pound of SO2 obtained from the Priority Reserve, and |
| – |
Paying a non-refundable mitigation fee of $12,000 per pound per day
for each pound of CO obtained from the Priority Reserve, and |
| – |
Submitting a complete application for a permit during calendar
years 2000, 2001, 2002, or 2003 and the EGF becoming fully operational
within 3 years after permitting, and |
| – |
Making a good faith effort to obtain offsets including ERCs, state
emissions bank credits, and credits from SIP approved credit generation
programs (limited to rates not to exceed the mitigation fee). |
CEQA Analysis
Pursuant to the California Environmental Quality Act (CEQA) Guidelines
§15164, the SCAQMD has prepared an Addendum to the November 2001 EA for the
Rule 1309.1 – Priority Reserve. The Addendum to the Final EA concludes that
the proposed changes would not create any new significant adverse impacts or
make substantially worse any existing significant adverse impacts generated
by the original project. The proposed modification does not change the
environmental analysis or conclusions in the previously certified Final EAs.
Pursuant to CEQA Guidelines §15164 (c), an addendum need not be circulated
for public review. The addendum is attached to this Board Letter. A copy of
the previously released CEQA document can be obtained from the SCAQMD’s
Public Information Center by calling (909) 396-2039. The previously
certified Final EA is being provided to Board Members for their review.
Socioeconomic Impacts
The socioeconomic analysis of the proposed amendments to Rule 1309.1 in
April 2001 performed a thorough socioeconomic assessment of the supply of
and demand for PM10 credits. A few projects identified at the time have not
materialized and the estimated total demand for EGF PM10 offsets was revised
downwards in the November 2001, Rule 1309.1 staff report. Furthermore, the
demand for PM10 offsets by the proposed project is 52% less than anticipated
in the November 2001, Rule 1309.1 staff report. Currently, only about 8% of
the amount anticipated in April 2001, and less than 10% of the amount
anticipated in November 2001, of the offset demand for Priority Reserve PM10
credits has been issued to qualified EGF’s. As such, the proposed project
demand for PM10 credits would have no additional impact on the current PM10
credit market beyond what has been analyzed in the April 2001 Rule 1309.1
socioeconomic assessment, which is incorporated herein by reference. There
are no additional socioeconomic impacts associated with this project.
AQMP and Legal Mandates
The California Health and Safety Code requires the AQMD to adopt an Air
Quality Management Plan to meet state and federal ambient air quality
standards in the South Coast Air Basin. In addition, the California Health
and Safety Code requires that the AQMD adopt rules and regulations that
carry out the objectives of the AQMP. While Proposed Amended Rule 1309.1 is
not a control measure included in the AQMP, its requirements are consistent
with the AQMP objectives.
Implementation Plan
No implementation issues are identified with this proposal.
Resource Impacts
The proposed amendments are not anticipated to have a significant impact
on staff resources.
Attachments
- Summary of Proposal
- Rule Development Flow Chart
- Key Contacts List
- Resolution
- Rule Language
- CEQA Addendum
/ / / |