|
PROPOSAL:
Proposed Amendments to SOx RECLAIM Program
(Regulation XX)
SYNOPSIS:
Proposed Amendments to Regulation XX RECLAIM will achieve additional SOx
reductions pursuant to the 2007 AQMP Control Measure #2007CMB-02. The proposed
amendments also address requirements for demonstrating Best Available Retrofit
Control Technology equivalency in accordance with California Health and Safety
Code §40440.
COMMITTEE:
Stationary Source Committee, June 20, 2008, June 19, 2009,
November 20, 2009, May 21, 2010, July 23, 2010, and September 24, 2010,
Reviewed. Refinery Committee, December 11, 2009, August 18, 2010 and September
22, 2010, October 14, 2010, Reviewed.
RECOMMENDED ACTIONS:
Adopt the attached resolution:
- Certifying the Final Program Environmental Assessment (PEA)
for Proposed Amended Regulation XX – Regional Clean Air
Incentives Market (RECLAIM); and
- Amending Proposed Rule 2002 – Allocations for Oxides of
Nitrogen (NOx) and Oxides of Sulfur (SOx).
Barry R. Wallerstein, D.Env.
Executive Officer
Background
Introduction The AQMD Board adopted the Regional Clean Air Incentives Market
(RECLAIM) program in October 1993. The purpose of the RECLAIM program is to
reduce NOx and SOx emissions through a market-based program. The program
replaced a series of existing and future command-and-control rules and was
designed to provide facilities with the flexibility to seek the most
cost-effective solution to reduce their emissions. AQMD staff is proposing
amendments to Regulation XX – RECLAIM to achieve additional SOx reductions
pursuant to the 2007 AQMP Control Measure CMB-02 and state law.
Specifically, the proposed amendments address requirements for 1) Best
Available Retrofit Control Technology (BARCT) in accordance with California
Health and Safety (H&S) Code §40440, and 2) a demonstration of equivalency to
command-and-control regulations, as required under H&S Code § 39616(c)(1).
Reductions in SOx will help the Basin attain the federal annual average PM2.5
standard by 2015, and the federal 24-hour average standard by 2020. Other
proposed rule amendments include clarifications and changes to the protocols.
Public Process
In a three-year rule development process for the proposed amendments from
2008-2010, staff conducted a Public Workshop on June 23, 2009; an Informational
Governing Board Hearing on January 8, 2010, and a Public Consultation Meeting on
September 8, 2010. Staff held numerous Working Group meetings with the
stakeholders, as well as individual meetings with WSPA and the refineries to
discuss issues related to the proposed amended rule. Staff presented its
proposal at six Stationary Source Committee meetings and four Refinery Committee
meetings for review. Staff released the first Preliminary Draft Staff Report in
April 2008. At the June 23, 2009 Public Workshop, staff released the Draft
Staff Report, the Notice of Preparation of the Draft Environmental Assessment,
and the Draft Rule 2002. On August 18, 2010, staff released its Draft Program
Environmental Assessment for a 45-day public review. On October 1, 2010, staff
released its revised Draft Staff Report and the Socioeconomic Analysis for a
30-day public review. Regarding feasibility and cost analyses, in 2008-2009,
staff contracted two consultants, ETS, Inc. and NEXIDEA to conduct independent
feasibility and cost analyses. In 2010, staff contracted a third consultant -
Norton Engineering Inc. (NEC) - to review the first two consultants’ analyses.
The consultants’ non-confidential reports are posted on the AQMD web page.
Affected Facilities
The proposed amendments will affect eleven major facilities: six refineries,
a coke calciner, two sulfuric acid plants, a container glass manufacturing
plant, and a cement plant. These eleven major facilities emitted 9.31 tons per
day (93% of the total emissions from the SOx RECLAIM universe.) These eleven
facilities hold 10.21 tons per day RTCs (87% of the total RTC holdings for the
SOx RECLAIM universe.) The refinery sector accounted for 76 % of the total
emissions and 73 % of the total available RTCs. Figure
1 [1] shows the emission distribution at these eleven facilities. The majority of
the emissions was generated from seven categories of sources: 1) fluid catalytic
cracking units; 2) sulfur recovery and tail gas treatment units; 3) refinery
boilers and heaters; 4) sulfuric acid manufacturing plants; 5) container glass
melting furnace; 6) coke calciner; and 7) cement kilns and a coal fired steam
boiler at a cement manufacturing facility.
FIGURE 1 2005 Emission Distribution

[1] The 2005 audited emissions for the entire SOx
RECLAIM universe were 10.04 tons per day. The total RTC Holdings for the
universe are 11.77 tons per day.
Staff Proposal
BARCT Levels
Table 1 shows staff’s proposed new BARCT
levels, emission reductions estimated from 2005 baseline, and the average
cost-effectiveness values estimated based on ETS/AEC’s and NEXIDEA’s
recommendations (the first figure in the cost-effectiveness range), and Norton
Engineering’s recommendations (the second figure in the cost effectiveness
range.) Figure 2 shows the present worth values for the 25-year equipment life,
estimated using the consultants’ input. The total investments were estimated to
be approximately $630 millions to $750 millions dollars. The weighted average
cost effectiveness spans between $16,000 per ton to $19,000 per ton SOx reduced
for this project. The cost effectiveness for individual source categories
ranges from $2,000 per ton to $50,000 per ton. It should be noted that WSPA
strongly disagrees with the analyses performed by staff and the consultants.
TABLE 1
Staff’s Proposed New BARCT Levels
|
|
New BARCT
|
Emission
Reductions(tons per day)
|
Cost Effectiveness
($/ton)
|
|
FCCUs
|
5 ppmv
|
2.88
|
20K - 21K
|
|
SRU/TGs
|
5 ppmv
|
0.73
|
31K - 45K
|
|
Sulfuric Acid
|
10 ppmv
|
1.03
|
2K – 3K
|
|
Coke Calciner
|
10 ppmv
|
0.28
|
10K - 23K
|
|
Container Glass
|
5 ppmv
|
0.19
|
5K
|
|
Cement Kilns
|
5 ppmv
|
0.25
|
19K - 27K
|
|
Coal Fired Boiler
|
95% reduction
|
0.00
|
4 K
|
FIGURE 2
Present Worth Values (for 25
years) Based on Consultants’ Input (Excluding Cost-Ineffective Controls of >$50
K per Ton)

RTC Reductions
To implement the proposed BARCT levels, staff is
recommending that RTC holdings be reduced by 5.7 tons per day or by 51.4 percent
beginning 2012 through 2019. When fully implemented, these RTC reductions are
expected to result in 5.4 tons per day actual emission reductions. This
proposal differs slightly than the staff proposal released on October 1, 2010
and was crafted based on the latest available data and fully complies with all
legal requirements.
The 5.7 tons per day RTC reductions will be distributed
among the 11 major facilities, investors, and 3 facilities that have more RTCs
holdings than originally allocated as of August 29, 2009. Staff proposes not to
shave the RTC holdings of the 18 remaining facilities. Any RTCs traded after
August 29, 2009 and prior to the Governing Board hearing date will be subject to
the proposed shave levels to ensure that no RTC holdings are inappropriately
traded or sheltered.
The 5.7 tons per day RTC reductions will be implemented
in four (4) phases over eight (8) years. Staff will submit the first 4 tons per
day of RTC reductions to EPA to satisfy the SIP commitment and help the Basin
meet the standard in 2015, and will submit the remaining 1.7 tons per day at a
later phase.
- Phase 1: 3.0 tons per day of reductions in compliance year 2013
- Phase 2: 4.0 tons per day of reductions in compliance year 2014
- Phase 3: 5.0
tons per day of reductions in compliance year 2017
- Phase 4: 5.7 tons per day of
reductions in compliance year 2019
In an effort to ensure early reductions for
the RECLAIM Program, facilities will be required to use SOx reducing catalysts
in the FCCUs no later than July 1, 2011 to achieve a limit of 25 ppmv. The use
of alternative controls is also allowed.
Safety Valves
To safeguard the
successful implementation of the SOx RECLAIM program, several necessary “safety
valves” are built in the proposed rule language: Staff is proposing set-aside
RTC accounts (i.e. non-tradable/non-usable) equivalent to the RTC reductions
called for by the specific compliance years that can potentially be made
available to the impacted facilities in the event RTC prices exceed the $50,000
per ton threshold (discrete credit). Staff commits to monitor the 12-month
rolling average RTC price and in the event the SOx RTC price exceeds $50,000 per
ton, staff will report to the Governing Board at a public hearing to be held no
more than 60 days from staff determination. At the public hearing, the
Governing Board will decide whether or not to convert any portion of the
non‑tradable/non-usable RTCs to tradable/usable RTCs and give that portion back
to the facilities so that it can be used for compliance with the facility cap.
In addition, staff will not submit any of the post-2015 emission reductions for
inclusion into the State Implementation Plan until the reductions have been in
effect for one full compliance year.
Key Issues
Although staff resolved most
of the outstanding issues relative to the staff proposal the following
discussion summarizes the key issues raised during the rule development phase by
the stakeholders: 1) costs for compliance and BARCT determination, 2) BARCT
determination for Owens-Brockway glass container manufacturing facility in
Vernon; 3) water and wastewater, 4) market viability, and 5) shaving methodology
for facilities that are not subject to new BARCT, and for facilities that are
subject to new BARCT. Staff’s responses to these key issues are summarized
below:
1) Costs for Compliance& BARCT Determination
As part of its proposal
included in the Set Hearing Board Package released on October 1, 2010, staff
proposed to reduce RTC by 6.1 tons per day (55% shave) representing 5.4 tons per
day actual emission reductions by 2019. WSPA commented that staff should not
pursue the 6.1 tons per day RTC reductions because WSPA estimated the cost of
compliance with this shave to be $1.637 billion dollars, of which $836 million
dollars would be for emission reductions under WSPA’s main strategy to comply
with the “programmatic” BARCT, and $801 million dollars would be for “other”
investments that must be implemented to achieve additional reductions within
WSPA member facilities to comply with the 55% shave.
Staff’s Response: Staff
has reviewed WSPA’s analysis and concluded that WSPA’s main strategy to meet the
“programmatic” BARCT is reasonable. However, staff also concluded that WSPA’s
assumption for an additional $801 million investment to implement “other”
measures to meet the 55% shave would not be reasonable or necessary. Staff has
identified cost‑effective off-site reductions which could be used to substitute
for cost-ineffective on‑site controls as provided under a market-based
cap-and-trade program such as RECLAIM. However, to provide additional margin of
safety, staff is proposing to increase the compliance margin to 18.5% and reduce
the shave from 55% to 51.4%. Summary of staff’s analysis is provided below.
WSPA’s Main Strategy.
Even though WSPA’s main strategy [2]
is different than staff’s main strategy on an equipment-per-equipment basis,
WSPA’s strategy would result in 3.81 tons per day actual emission reductions at
a cost of $836 million and a cost-effectiveness of $24K per ton. In comparison,
staff’s proposed main strategy would result in 3.92 tons per day actual emission
reductions at a cost of between $561 million - $638 million and a
cost-effectiveness of $16K - $18K per ton. On this basis, staff believes that
the “programmatic” BARCT strategy proposed by WSPA is similar to staff’s
proposal since it will achieve similar reduction levels through cost-effective
measures.
[2] WSPA’s main
strategy includes 1) FCCUs would use 2 WGSs and SOx reducing additives to meet 5
ppmv – 35 ppmv; 2) SRU/TGs would use 2 WGSs and have process modifications to
meet 5 ppmv - 25 ppmv; 3) 1 WGS and other process modification at other units.
WSPA’s “Other” Strategies.
In its analysis presented to the
Refinery Committee on October 14, 2010, staff concluded that the two “other”
control strategies for a SRU/TG and fuel gas treatment proposed by WSPA at a
cost-effectiveness of $213,000 per ton and $100,000 per ton would not be
reasonable strategies to implement. However, two “other” strategies proposed by
WSPA related to CEMS improvements and RTC holdings surrendered are very
cost-effective at $1,686 - $6,805 per ton. The two “other” cost‑effective
strategies amounted to $81 million dollars. With the main strategy and the two
“other” cost-effective strategies in combination, WSPA members could achieve
5.31 tons per day reductions at $917 million and at an average
cost-effectiveness of $18,925 per ton. However, WSPA members would only need
5.17 tons per day reduction to meet a 55% shave. Therefore, it is only
reasonable to conclude that an investment of $917 million, not $1.637 billion
estimated by WSPA, would be more than adequate to meet the proposed 55% shave
and would generate 0.14 tons per day surplus RTCs. Nevertheless, to address
concerns relative to safety margin, staff has modified its proposal to increase
the compliance margin to 18.5% and reduce the shave from 55% to 51.4% which will
provide facilities with additional flexibility and the ability to meet the
proposed reduction target at less costs than those estimated above. In
addition, staff estimated that there would be approximately 1.45 tons per day
potentially available surplus RTCs[3] in the market from
other sources after the 51.4% shave, which would raise the pool of surplus
credits to 1.6 tons per day.
[3] The 1.47 tpd potentially available RTCs
post-shave in the market comprised of:
- 0.21 tpd post-shave remaining unused
RTCs (which is calculated as follows: The surplus RTCs estimated
from the 2005 baseline are 1.73 tpd (11.77 – 10.04 = 1.73 tpd).
WSPS already accounted for 1.30 tpd surplus RTC in their
strategy, therefore the remaining unused RTCs are 1.73 – 1.30 =
0.43 tpd pre-shave and (0.43 tpd)(0.486) = 0.21 tpd post shave)
- 0.0009 tpd post shave hold by
non-RECLAIM investors. (As of October 14, 2010, there are only
two remaining investors that are non-RECLAIM facilities, and
these two investors hold approximately 1,306 lbs of RTCs
pre-shave or 0.002 tpd pre-shave or 0.0009 tpd post-shave.)
- 0. 60 tpd from non-refinery sector.
(Assuming that the non-refineries would install control
technologies proposed by either WSPA to meet the 51.4% shave;
and would have surplus RTCs to sell in the market.)
- 0.66 tpd from refinery sector.
(Assuming that the refineries would install control technologies
proposed by either WSPA to meet the 51.4% shave; and would have
surplus RTCs to sell in the market.)
2) BARCT Determination for
Owens-Brockway Container Glass Facility in Vernon
Owens-Brockway commented that
staff incorrectly determined the BARCT for glass melting furnaces. BARCT for
glass melting furnaces should be at 80% not 95% (or 5 ppmv). Owens-Brockway
commented that the packed bed scrubbers recommended would not work; the pressure
drop introduced by the wet gas scrubbers was not considered; the costs of
$225,000 to handle waste water stream were inadequate; other costs (e.g. CEMS,
stack, permitting costs) were not included; and other analyses (e.g. NSR for
other pollutants, Rule 1401 requirements) were not analyzed.
Staff’s Response:
Staff disagrees with the commenter. Staff’s feasibility analysis concludes that
today’s BARCT is 5 ppmv (95% control efficiency or more). The proposed BARCT
for glass facility has been achieved in practice at a container glass
manufacturing facility in Seattle Washington. Relative to the control equipment
configuration for the Owens-Brockway facility in the South Coast basin, the
consultant (ETS) recommended the removal of the two dry scrubbers located
upstream of the ESPs, and their replacement with two wet scrubbers (packed bed)
positioned downstream of the ESPs. The ESPs located upstream of the packed bed
scrubbers will be highly efficient in controlling particulate matter, and thus
would provide protection for the packed bed scrubbers from clogging. In the
consultant’s analysis, a fan was provided to overcome the pressure drop across
the wet scrubbers and costs for a new stack were included. The cost
effectiveness of this project is about $5,198 per ton SOx removed, and therefore
other marginal additional costs such as adding new CEMS and permitting costs
would not alter the project’s cost-effectiveness significantly. The consultant
(ETS) estimated the equipment costs ($225,000) and annual operating costs for a
waste water treatment based on information provided by Manufacturer D who cited
from their relevant experience with a glass container facility in Seattle,
Washington. Nevertheless, to address concerns expressed by Owens-Brockway and
other facilities relative to additional margin for safety, staff has modified
its proposal to increase the compliance margin to 18.5% and reduce the proposed
shave from 55% to 51.4%. Relative to the issues such as NSR, staff recommends
that they should be handled at the permitting phase not at the rule development
phase of this project. Staff commits to help this and all other impacted
facilities during permitting to ensure the successful implementation of this
very important program. Staff would further like to remind the commenter that
the District’s NSR Program (Regulation XIII) includes provisions that shields
installation of pollution control equipment from the applicability of certain
other NSR requirements.
3) Water & Wastewater Impacts
Stakeholders commented
that the water and wastewater impacts of the project would be significant.
Staff’s Response:
Industry argued that staff proposal will result in
significant increases on water demand and wastewater impacts due to the use of
wet gas scrubbers. If wet gas scrubbers are used to comply with the proposed
rule, staff estimated that the total water demand will increase by approximately
1 million gallons per day or 3 acre feet per day, but increased water demand
over current water usage at affected facilities is well below the SCAQMD’s
significance threshold of 5 million gallons per day of total increased water
demand (i.e. potable water, recycled water, and groundwater). The information
that staff received to date from the water purveyors and their 2005 Urban Water
Management Plans is that there are adequate supplies to meet the total water
demand, and use of recycled water is highly recommended if available. Relative
to the wastewater impact, staff’s analysis indicates that the overall wastewater
increase will be less than 2% and that the facilities have adequate wastewater
treatment capacity to treat the increase, and no modifications to any existing
wastewater discharge permits are anticipated. WSPA continues to strongly
disagree with staff’s analyses.
3) Market Viability
Stakeholders commented
that there were not enough trading partners, the SOx market was very competitive
and reserved, and there was an uneven distribution of RTC holdings.
Staff’s
Response:
For a market based incentive program, staff is required by the H&S
codes to conduct periodic BARCT reassessment and demonstrate equivalency with
command-and-control rules which would otherwise be developed as a result of
BARCT reassessment. To ease the issues identified by the stakeholders, staff is
proposing to return a portion of the reductions to the facilities as a
compliance margin (18.5%). Similar approach was also utilized as part of the
2005 NOx RECLAIM amendments. Accounting for the fact that the SOx RECLAIM
market is a lot less robust than the NOx RECLAIM market, staff is proposing a
compliance margin of 18.5%. In addition, staff is proposing to establish a
set-aside, non-tradable reserve that could be tapped in when RTC value in the
open market reach a certain level. Staff believes that compliance with a
facility cap still provides the facilities more operational flexibility than
being subject to stringent requirements in command-and-control rules and
regulations.
4) Shaving Methodology
Facilities with no equipment subject to
new BARCT commented that the uniform shave was not equitable, would create
significant difficulties for them to stay in compliance, and indicated that they
had limited ability to buy RTCs from large facilities. While WSPA and the
refineries that are subject to new BARCT argued strongly during the rule
development process in 2008-2009 for the use of a shave methodology that was
consistent with that used during the 2005 NOx RECLAIM amendment. During the
later phase of the rule development process, they commented that staff should
use the 2005 as baseline for the shave, not shave the 1.98 tpd RTCs converted
from ERCs and portion reserved for Clean Fuel projects, and not set new BARCT
for SRU/TGs and cement kilns.
Staff’s Response:
Because of the non-uniform
emissions and RTC distributions in the SOx RECLAIM market (11 major facilities
hold almost 90% of the RTCs and contribute more than 90% of emissions, and the
remaining 21 facilities hold only 6% of the RTCs and contribute about 6% of
emissions), a uniform percent shave cross the board is not the ultimate
solution. The 21 facilities that have no equipment subject to the new BARCT
cannot reduce their emissions further, cannot sustain operation since they had
limited ability to buy RTCs from large facilities, and therefore cannot remain
in compliance after the shave. To keep the 21 facilities active in the SOx
market, staff is proposing to not shave the RTC holdings for these facilities if
the RTC holdings are below their initial allocations provided to them at the
start of the RECLAIM program. However, the amount of RTC holdings above their
initial allocation will be shaved at the same rate as other 11 facilities and
investors. With this approach, staff estimated that the 11 facilities will have
a shave of 51.4%, 18 of the 21 facilities will be exempt totally from the
shave, and 3 of the 21 facilities that have RTC holdings above their initial
allocations will be shaved accordingly. Any trading from August 29, 2009 to
the Governing Board hearing date will also be subject to the shave to ensure
that RTC holdings are not inappropriately traded to or sheltered by a third
party to avoid the shave.
California Environmental Quality Act (CEQA) Analysis
Pursuant to California Environmental Quality Act (CEQA) Guidelines §15252 and
§15168 and AQMD Rule 110, the SCAQMD has prepared a Program Environmental
Assessment (PEA) for proposed amended Regulation XX. Only the topics of air
quality and hydrology (water demand) were identified in the Draft PEA as
exceeding the SCAQMD’s significance thresholds. The Draft PEA was released for
a 45-day public review and comment period from August 18, 2010 to October 1,
2010. Three comment letters were received from the public relative to the Draft
PEA. Since the release of the Draft PEA, responses to the comments have been
prepared and included in the document. Also, minor modifications have been made
to the document. None of the modifications alter any conclusions reached in
the Draft PEA, nor provide new information of substantial importance relative to
the draft document. Further, the modifications do not constitute significant
new information that would require recirculation of the Draft PEA pursuant to
CEQA Guidelines §15088.5. Therefore, the document is a now a Final PEA and is
included as an attachment to this Governing Board package.
Socioeconomic
Analysis
The socioeconomic analysis of the proposed amended SOx RECLAIM was
based on the 55 percent shave of SOx RTC holdings. Eleven facilities would be
affected, the majority of which are located in Los Angeles County. The average
annual compliance cost of the 55 percent shave ranged from $32 to $42 million
with few job impacts on the local economy. The new proposed 51.4 percent shave
would lower the compliance cost. The job impact of the new proposal would be
within the noise of the economic model used for the SOx RECLAIM analysis. WSPA
prepared its own socioeconomic analysis, including a scenario where a mid-size
refiner closes. Staff reviewed this issue and pointed out a number of
mitigating factors relative to any potential job impacts.
Implementation and
Resources
It is expected that there will be a temporary workload increase due to
applications submitted for installing new control equipment or
retrofitting/modifying existing processes and there might be an increase in RTC
trading activities. However, current AQMD resources are adequate to implement
the proposed rule.
Attachment 1
(ZIP, 25m)
- Summary of Proposal
- Rule
Development Process
- Key Contact List
- Resolution and Attachment 1
- Rule Language for PAR 2002 -
- Final Staff Report - SOx RECLAIM,
Part 1 – BARCT Assessment & RTC Reductions Analysis, and Part 2 – Summary of
Consultants’ Analyses
- Program Environmental Assessment
- Socioeconomic
Analysis
Attachment 2
Errata
|